You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using the following project status chart to calculate project current CV: Activity | Day 1 | Day 2 | Day 3 | Day 4 | Status End of Day 3 | Side 1 | S-------F | | | | Complete, spent $1,000 | Side 2 | | S-------PF | -------F | | Complete, spent $1,200 | Side 3 | | | PS---S---PF | | 50% done, spent $600 | Side 4 | | | | PS-------PF | Not yet started

Dễ6 phương ánTỷ lệ đúng 70%20 lượt làmCó lời giảiXuất hiện trong 2 bộ đề

A·B·C·DCác phương án trả lời

ACV = -$500
CV = -$300Đúng
CCV = -$200
DCV = $200
ECV = $500
FCV = $300

Giải thích chi tiết

Đáp án đúng: CV = -$300. EV = 1.000 (cạnh 1) + 1.000 (cạnh 2) + 500 (cạnh 3 xong 50%) = 2.500. AC = 1.000 + 1.200 + 600 = 2.800. CV = EV − AC = −300.