Your team has identified a risk that is a threat to your ability to successfully meet project objectives. The risk involves team members from your company performing work which requires training, certification, and many hours of experience. You have one newly certified team member and others who are still in training. Which do you think is your best response to this risk?
Dễ4 phương ánCó lời giảiXuất hiện trong 1 bộ đề
A·B·C·DCác phương án trả lời
Acknowledge your lack of expertise and set aside some contingency reserve to cover the risk.Đúng
BChange the scope of the project so that this type of work is excluded and introduce a new risk, that of an unhappy sponsor.
CLet the team do the work and see what happen, do not prepare any other response.
DHave budget to hire external resources and there is a vendor you can hire who specialized in this type of work, hire them.
Giải thích chi tiết
Khi nhận ra một rủi ro có thể ảnh hưởng đến khả năng hoàn thành mục tiêu của dự án, bạn cần có kế hoạch cụ thể để đối phó. Trong trường hợp này, rủi ro liên quan đến việc thành viên trong đội không có đủ kỹ năng, chứng chỉ và kinh nghiệm cần thiết để thực hiện công việc. Để giải quyết vấn đề này, bạn nên thừa nhận sự thiếu sót về kỹ năng và lập kế hoạch dự phòng để đối phó với rủi ro này. Điều này có nghĩa là bạn cần xác định mức độ rủi ro và lập kế hoạch để giảm thiểu tác động của nó. Bạn có thể lập kế hoạch dự phòng bằng cách phân bổ thêm ngân sách hoặc tìm kiếm sự hỗ trợ từ bên ngoài.