You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using the following project status chart to calculate project current BAC: [Side 1: hoàn thành, chi $1,000 | Side 2: hoàn thành, chi $900 | Side 3: xong 50%, chi $600 | Side 4: xong 75%, chi $600]
6 phương ánCó giải thíchDễ
Các phương án trả lời
Chọn một phương ánLời giảiChọn phương án để mở
Đáp án đúng: BAC = $4,000. BAC (Budget At Completion) = tổng ngân sách cả dự án = 4 cạnh × $1,000 = $4,000. BAC không phụ thuộc tiến độ hay tiền đã chi.
Cùng chủ đề
True or False: A Project is defined as being unique and temporary, with a defined start and finish.Có lời giảiCâu hỏiWe discussed four types of organization structures, they are:Có lời giảiCâu hỏiA project manager's primary responsibility is to deliver the product of the project within project constraints. Actions taken and changes made to the benefit of one constraint could negatively affect another. Which of the following best describes the major constraints on a project?Có lời giảiCâu hỏiCả 311 câu của chủ đề311 câu
Xuất hiện trong 1 bộ đề
Đi tiếp từ đây