You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using the following project status chart to calculate project current SV: [Side 1 — actual start and actual finish on Day 1; status end of day 3: Complete, spent $1,000] [Side 2 — actual start Day 2, planned finish end of Day 2, actual finish Day 3; status end of day 3: Complete, spent $1,200] [Side 3 — planned start and actual start Day 3, planned finish end of Day 3; status end of day 3: 50% done, spent $600] [Side 4 — planned start and planned finish Day 4; status end of day 3: Not yet started]

6 phương ánCó giải thíchTrung bình

Các phương án trả lời

Chọn một phương án
Lời giảiChọn phương án để mở
Đáp án đúng: SV = -$500. Công thức: SV = EV − PV. Tính PV (giá trị theo kế hoạch tới cuối ngày 3): theo kế hoạch bốn cạnh làm nối tiếp mỗi cạnh một ngày, nên tới hết ngày 3 lẽ ra ba cạnh đã xong ⇒ PV = 3 × 1.000 = 3.000 USD. Tính EV (giá trị thu được, luôn tính theo NGÂN SÁCH của phần việc đã hoàn thành, không tính theo tiền đã tiêu): cạnh 1 xong = 1.000, cạnh 2 xong = 1.000, cạnh 3 mới 50% = 500, cạnh 4 chưa bắt đầu = 0 ⇒ EV = 2.500 USD. Vậy SV = 2.500 − 3.000 = −500 USD, số âm nghĩa là dự án ĐANG CHẬM tiến độ. Lưu ý cái bẫy: các khoản đã chi (1.000 + 1.200 + 600 = 2.800 USD) là AC, chỉ dùng để tính CV và CPI, không được đưa vào phép tính SV.

Cùng chủ đề

Xuất hiện trong 1 bộ đề